Question: A project is in progress with a team that is new to agile approaches. After the first sprint review, the team performance begins slipping, and
A project is in progress with a team that is new to agile approaches. After the first sprint review, the team performance begins slipping, and the conclusion is that there is not an adequate flow of work for the team. What should the project manager do? Change the project approach to hybrid. Provide the product owner with training. Submit a change request to rebaseline the project. Discuss the issue with the stakeholders
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
