Question: project is in progress with a team that is new to agile approaches. After the first sprint review, the team performance begins slipping, and the
project is in progress with a team that is new to agile approaches. After the first sprint review, the team performance begins slipping, and the conclusion is that there is not an adequate flow of work for the team. What should the project manager do? Change the project approach to hybrid. Submit a change request to rebaseline the project. Provide the product owner with training. Discuss the issue with the stakeholders