Question: A project is nearing the expected completion date, but it is behind schedule. The project manager has decided to fast-track the resources. Which of the

  1. A project is nearing the expected completion date, but it is behind schedule. The project manager has decided to fast-track the resources. Which of the following impacts will MOST likely occur? (SELECT TWO)
  • Cost will increase
  • Scope will increase
  • Schedule will decrease
  • Risk will decrease
  • Budget will increase
  • Quality will increase
  1. During the risk assessment process, the qualitative analysis results in the majority of risk scores being rated as medium. What of the following is the BEST course of action?
  • Increase the contingency reserve
  • Add the risks to the watch list
  • Establish and monitor trigger conditions
  • Assign the sponsor as the primary risk owner
  1. A project team member has completed an assigned task on time. After updating the project schedule, which of the following steps should the project manager take NEXT?
  • Send an updated schedule to the CCB
  • Send a project status update to the sponsor
  • Release the team members to the functional manager
  • Notify the team members to begin successor tasks
  1. A customer has requested a change in an active project. Which of the following actions should the project manager take FIRST?
  • Gather input from the team
  • Inform the end user of the change
  • Submit the change request to the project sponsor
  • Update the change log

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!