Question: A project is nearing the expected completion date, but it is behind schedule. The project manager has decided to fast-track the resources. Which of the
- A project is nearing the expected completion date, but it is behind schedule. The project manager has decided to fast-track the resources. Which of the following impacts will MOST likely occur? (SELECT TWO)
- Cost will increase
- Scope will increase
- Schedule will decrease
- Risk will decrease
- Budget will increase
- Quality will increase
- During the risk assessment process, the qualitative analysis results in the majority of risk scores being rated as medium. What of the following is the BEST course of action?
- Increase the contingency reserve
- Add the risks to the watch list
- Establish and monitor trigger conditions
- Assign the sponsor as the primary risk owner
- A project team member has completed an assigned task on time. After updating the project schedule, which of the following steps should the project manager take NEXT?
- Send an updated schedule to the CCB
- Send a project status update to the sponsor
- Release the team members to the functional manager
- Notify the team members to begin successor tasks
- A customer has requested a change in an active project. Which of the following actions should the project manager take FIRST?
- Gather input from the team
- Inform the end user of the change
- Submit the change request to the project sponsor
- Update the change log
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock