Question: a project is partially complete. the work package estimate was$297000,the contingency reserve is 34.5% and the management reserve is38.5% of the baseline. There are 2
Step by Step Solution
There are 3 Steps involved in it
To calculate the remaining balance left in the contingency reserve we need to follow these steps Ste... View full answer