Question
1 Approved Answer
a project is partially complete. the work package estimate was$297000,the contingency reserve is 34.5% and the management reserve is38.5% of the baseline. There are 2
a project is partially complete. the work package estimate was$297000,the contingency reserve is 34.5% and the management reserve is38.5% of the baseline. There are 2 approved change request based on known risks,CR1 which is $7400 and CR2 which is $141000.There is also a 3rd change request pending approval,CR3 which is $131500. What would be the remaining balance left in our contingency reserve if the only funds used from the contingency reserve was 31% of CR
Step by Step Solution
There are 3 Steps involved in it
Step: 1
To calculate the remaining balance left in the contingency reserve we need to follow these steps Ste...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started