Question

1 Approved Answer

a project is partially complete. the work package estimate was$297000,the contingency reserve is 34.5% and the management reserve is38.5% of the baseline. There are 2

a project is partially complete. the work package estimate was$297000,the contingency reserve is 34.5% and the management reserve is38.5% of the baseline. There are 2 approved change request based on known risks,CR1 which is $7400 and CR2 which is $141000.There is also a 3rd change request pending approval,CR3 which is $131500. What would be the remaining balance left in our contingency reserve if the only funds used from the contingency reserve was 31% of CR

Step by Step Solution

There are 3 Steps involved in it

Step: 1

To calculate the remaining balance left in the contingency reserve we need to follow these steps Ste... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

An Introduction to Management Science Quantitative Approach to Decision Making

Authors: David R. Anderson, Dennis J. Sweeney, Thomas A. Williams, Jeffrey D. Camm, James J. Cochran

15th edition

978-1337406529

More Books

Students also viewed these General Management questions

Question

= What do you conclude from the above?

Answered: 1 week ago