Question: A project is planned for six months at the total cost of $120,000. It is expected that cost of the project will incur equally over
A project is planned for six months at the total cost of $120,000. It is expected that cost of the project will incur equally over the six months. It is month 2 and your team has spent $30,000 and they are about 30% complete. The PV of this project is