Question: 1 . Question 1 A project is planned for six months at the total cost of $ 1 2 0 , 0 0 0 .
Question
A project is planned for six months at the total cost of $ It is expected that cost of the project will incur equally over the six months. It is month and your team has spent $ and they are about complete. The EV of this project is:
point
$
$
$
None of the above