A project is represented by the following diagram: 1. The expected duration of this project is: A.12
Fantastic news! We've Found the answer you've been seeking!
Question:
A project is represented by the following diagram:
1. The expected duration of this project is:
A.12
B.17
C.20
D.36
E.77
2. The critical path for the network shown is:
A. a-c-g.
B. a-d-f-g.
C. a-d-h-i.
D. b-e-f-g.
E. b-e-h-i.