Question: A project is scheduled to be completed in a task at 4 hours. At this point, the time spent was 8 hours. The hourly rate

A project is scheduled to be completed in a task at 4 hours. At this point, the time spent was 8 hours. The hourly rate is set to be $ 50 per hour.

The estimation for completion is 1 hour more, that caused the earning to be 91.5% of what was planned. What is the planned value PV of the project?

What is the actual cost AC of the project?

What is the earned value EV of the project?

Find the SPI and CPI of the project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!