Question: A project is shown below. D STA B H FIN K The duration of activities are shown below. activity = D, duration = 21 days

A project is shown below. D STA B H FIN K The
A project is shown below. D STA B H FIN K The duration of activities are shown below. activity = D, duration = 21 days activity = E, duration = 49 days activity = F, duration = 41 days activity = G, duration = 40 days activity = H, duration = 30 days activity = K, duration = 40 days LF of G = 111 LF of H = 118 LF of K = 100 The latest finish time of activity C is at the end of day