Question: A project is undergoing major restructuring, which includes recruiting a new project manager. Halfway through the restructuring, the project sponsor has approved the assessment report

A project is undergoing major restructuring, which includes recruiting a new project manager. Halfway through the restructuring, the project sponsor has approved the assessment report and confirmed the short-term actions and scope of changes required to address the many project issues.
What should the new project manager do next?
Question 7 options:
Wait for the project sponsor to decide how to communicate the actions and project key changes.
Update the project organization chart, risks, communications, and stakeholder engagement plans.
Present the details of the project assessment report and key action items to the project team and stakeholders to ensure their support.
Do nothing, because the team members were part of the project assessment report and should be aware of the upcoming changes.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!