Question: A project is underway and is 50% completed. An essential project team member requests leave on personal grounds for a month and a half. What
A project is underway and is 50% completed. An essential project team member requests leave on personal grounds for a month and a half. What should the project manager do first? SELECT THE CORRECT ANSWER Check with this team member to see if the leave can be postponed Discuss the issue with the functional manager and request a replacement Assess how the leave will impact on the project Refer to the resource management plan