Question: A project management artifact that captures Risks, Issues alongside probability of occurrence of risks and their impact but does not capture preventive or corrective actions

A project management artifact that captures Risks, Issues alongside probability of occurrence of risks and their impact but does not capture preventive or corrective actions is______. Group of answer choices Risk register RAID log Failure Modes Effect Analysis Document Probability Impact Matrix