Question: A project manager and key team members were preparing a RACI chart for the major project work packages and activities. In each row they only
A project manager and key team members were preparing a RACI chart for the major project work packages and activities. In each row they only assigned one Afor Accountable to a single resource. Why did they feel it was necessary for only one person to be assigned the primary accountability for each activity?
a Because only one person should do the work on each activity or work package
b Because the project manager is always the person who is accountable for each activity or work package
c Because if more than one person has accountability, it is too easy for them to blame each other when something goes wrong
d Because there are rarely enough people on a project team to have more than one person be accountable
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock