Question: A project manager and project team have brought a project back on track after mapping and removing impediments. During the current sprint, the team reported
A project manager and project team have brought a project back on track after mapping and removing impediments. During the current sprint, the team reported that an impediment that previously caused major delays has appeared again. The leam tried implementing the same mitigation tasks that worked previously. However, the tasks are not having the same result with the impediment. Time Remaining 74:03 =179 of 180 A Elag for Review What should the project manager do? Use the contingency budget to implement schedule compression Escalate the issue with an impediment to the project sponsor Implement the mitigation plans listed in the organizational process assets (OPAs) Reassess the issue as part of monitoring and controlling
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
