Question: A project manager begins to prepare the project management plan after receiving the project charter. There is currently NO historical information in the project management
A project manager begins to prepare the project management plan after receiving the project charter. There is currently NO historical information in the project management office (PMO). What next step should the project manager take in this scenario? Choose only ONE best answer. A Utilize analogous estimating. B Seek advice from experts in the field. C Organize an initial kick-off call. D Request input from the project sponsor