Question: A project manager creates a budget. They determine the amount of buffer funds the project likely needs for completion. What is this budget component?
A project manager creates a budget. They determine the amount of buffer funds the project likely needs for completion. What is this budget component?
Step by Step Solution
There are 3 Steps involved in it
This budget component is known as a contingency reserve A contingency reserve is an ... View full answer