Question: A project manager distributes weekly earned value metrics to communicate budget performance to the project stakeholders is an example of: Corrective action requirements Work performance
A project manager distributes weekly earned value metrics to communicate budget performance to the project stakeholders is an example of: Corrective action requirements Work performance reports Forecasting adjustment requirements New risk assessment