Question: A project manager estimated that her development team would need 4 0 hours to complete a project milestone. The actual number of hours required at

A project manager estimated that her development team would need 40 hours to complete a project milestone. The actual number of hours required at project completion was 50. This is known as a
Risk
Baseline
Deliverable
Variance