A project manager finds that a particular activity has a slack of 1 week when the activity
Fantastic news! We've Found the answer you've been seeking!
Question:
A project manager finds that a particular activity has a slack of 1 week when the activity is presented in a network diagram in CPM (Critical Path Method based on a deterministic model). Which statement is correct?
"If the activity is finished 1 week earlier, it becomes critical"
"If the activity is delayed by 1 week, it becomes non-critical"
"If the activity is delayed by 1 week, it becomes critical"
The activity can never become critical regardless of the delay.
The activity can never become non-critical regardless of the delay.
Related Book For
Project Management A Systems Approach to Planning Scheduling and Controlling
ISBN: 978-0470278703
10th Edition
Authors: Harold Kerzner
Posted Date: