Question: A project manager finds that a particular activity has a slack of 1 week when the activity is presented in a network diagram in CPM
A project manager finds that a particular activity has a slack of 1 week when the activity is presented in a network diagram in CPM (Critical Path Method based on a deterministic model). Which statement is correct?
"If the activity is finished 1 week earlier, it becomes critical"
"If the activity is delayed by 1 week, it becomes non-critical"
"If the activity is delayed by 1 week, it becomes critical"
The activity can never become critical regardless of the delay.
The activity can never become non-critical regardless of the delay.
Step by Step Solution
3.50 Rating (170 Votes )
There are 3 Steps involved in it
Lets analyze the question using the principles of Critical Path Method CPM 1 Slack or Float In CPM s... View full answer