Question: A project manager for a small construction company has a project that was budgeted for US $ 1 3 0 , 0 0 0 over

A project manager for a small construction company has a project that was budgeted for US $130,000 over a six-week period project should have cost US $60,000 to date . However, it has cost US $90,000 to date . The project is also behind schedule, beca not accurate . Who has PRIMARY responsibility to solve the problem?