Question: A project manager has completed the following steps: Finished a major IT deployment project, confirmed with the release manager that all systems are working, confirmed
A project manager has completed the following steps: Finished a major IT deployment project, confirmed with the release manager that all systems are working, confirmed that functionality has been verified by the quality assurance team, informed the customer. Which next step should the project manager take?
Step by Step Solution
There are 3 Steps involved in it
The next step the project manager should take is to add the lessons ... View full answer