Question: A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What
A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situation? Risk acceptance Risk avoidance Risk transfer * Risk mitigation