Question: A project manager has developed the following data on a project tasks and duration. Please create an AON diagram, identify the critical path and the

A project manager has developed the following data on a project tasks and duration. Please create an AON diagram, identify the critical path and the expected project duration. The customer has asked for a 95% confidence on the project completion date.Calculate the number of additional weeks the project manager needs to make that commitment.

Time estimation in weeks
Task Predecessor optimistic Most likely Pessimistic
A 3 4 5
B A 1 8 15
C A 2 4 6
D A 4 8 12
E B 7 9 11
F C,B 2 5 8
G E,D 5 7 9
H F,G 4 7 10