A project manager has developed the following data on a project tasks and duration. Please create an AON diagram, identify the critical path and the expected project duration. The customer has asked for a 95% confidence on the project completion date.Calculate the number of additional weeks the project manager needs to make that commitment.
| Time estimation in weeks | ||||
| Task | Predecessor | optimistic | Most likely | Pessimistic |
| A | 3 | 4 | 5 | |
| B | A | 1 | 8 | 15 |
| C | A | 2 | 4 | 6 |
| D | A | 4 | 8 | 12 |
| E | B | 7 | 9 | 11 |
| F | C,B | 2 | 5 | 8 |
| G | E,D | 5 | 7 | 9 |
| H | F,G | 4 | 7 | 10 |