Question: A project manager has developed the following data on a project tasks and duration. Please create an AON diagram, identify the critical path and the

A project manager has developed the following

A project manager has developed the following data on a project tasks and duration. Please create an AON diagram, identify the critical path and the expected project duration. The customer has asked for a 95% confidence on the project completion date. Calculate the number of additional weeks the project manager needs to make that commitment. Predecessor Task A Time estimation in weeks optimistic Most likely Pessimistic 3 4 5 1 8 15 B A A 2 4 6 D 4 8 12 11 7 9 9 E F A B , E,D F,G 2 5 8 G 5 7 9 H 4 7 10

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!