Question: A project manager has discovered that three tasks are on the critical path for a particular project. She has developed the time estimates (in days)

A project manager has discovered that three tasks
A project manager has discovered that three tasks are on the critical path for a particular project. She has developed the time estimates (in days) shown in the table below. The customer has offered a $10,000 bonus if the project is completed within 14 days. What is the probability that the bonus will be earned? A. Approximately 85 percent 8. Approximately 5 percent c. Approximately 2.3 percent D. Approximately 977 percent