Question: A project manager has discovered that three tasks are on the critical path for a particular project. She has developed the time estimates ( in
A project manager has discovered that three tasks are on the critical path for a particular project. She has developed the time estimates in days shown in the table below. Complete the table and determine the expected completion time for the project.
tableTasktableBestCasetableMostLikelytableWorstCasetableExpectedDurationtableStandardDeviationtableStandardDeviationSquaredABC
A days
B days
C days
D days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock