Question: A project manager has identified the following: Four critical risks with a high - impact. Four specific resources necessary for addressing the risks. The resources
A project manager has identified the following:
Four critical risks with a highimpact.
Four specific resources necessary for addressing the risks.
The resources are committed to another project with critical deliverables.
The project manager must find a solution to address these risks immediately. Which actions should the project manager take? Select one.
Question options:
Option D
Create a contingency reserve to solve the potential schedule delay.
Mitigate the possible impact.
Option C
Accept the risks.
Monitor these risks often to reduce potential impact.
Option B
Contract a thirdparty vendor.
Assign this vendor to these tasks.
Option A
Contact the functional manager.
Evaluate the resources' availability to negotiate task crashing or rescheduling.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock