Question: Project manager A identifies three critical risks with probability of a high impact on the schedule and budget of project A this project is producing

Project manager A identifies three critical risks with probability of a high impact on the schedule and budget of project Athis project is producing critical deliverables for the company. The team meets to devise a solution for the risks and decides that three specific resources will be required to address the risks. However, these resources are already committed to a separate project, which is managed by project manager B. Which party should the project manager work with first to find a solution?