Question: A project manager has just learned that a supplier is currently running low on required materials for a project. The supplier is very confident that
A project manager has just learned that a supplier is currently running low on required materials for a project. The supplier is very confident that the materials will be restocked before they are needed for the project. The project manager decides to continue with the vendor rather than finding a new one. What kind of risk mitigation strategy is this? 1 point Avoiding risk Controlling risk Accepting risk Transferring risk