Question: A project manager has just taken over the project from another project manager during project execution. The previous project manager created a project budget, determined
A project manager has just taken over the project from another project manager during project execution. The previous project manager created a project budget, determined communications requirements, and went on to complete work packages. What should the new project manager do NEXT? Select one a. Identify quality standards b. Began the Identify Risks process. c. Coordinate completion of work packages d.Execute the project management plan O age Next page MacBook Air ... so Dll DO