Question: A project manager has just taken over the project from another project manager during project executing. The previous project manager created a project budget, determined

A project manager has just taken over the project from another project manager during project executing. The previous project manager created a project budget, determined communications requirements, and went on to the complete work packages task. What should the new project manager do next?

A. Coordinate completion of work packages.

B. * Identify quality standards.

C. Begin the Identify Risks process.

D. Validate scope.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Managers Questions!