Question: A project manager has just taken over the project from another project manager during project executing. The previous project manager created a project budget, determined
A project manager has just taken over the project from another project manager during project executing. The previous project manager created a project budget, determined communications requirements, and went on to the complete work packages task. What should the new project manager do next?
A. Coordinate completion of work packages.
B. * Identify quality standards.
C. Begin the Identify Risks process.
D. Validate scope.