Question: A project manager has mapped out that in their project there are 4 paths in the network to get from Project Start to Project Finish.

A project manager has mapped out that in their project there are 4 paths in the network to get from Project Start to Project Finish. Path ACI which takes 9 days, path BDE which takes 11 days, path FK which takes 8 days, and path HJ takes 2 days. Which of these four paths has a slack (float) time of 3 days? Select answer.
Question 13 options:
ACI
BDE
FK
HJ
None of these paths have a slack time of 3 days