Question: A project manager has mapped out that there are 4 paths in the schedule network diagram to get from Project Start to Project Finish. Path

A project manager has mapped out that there are 4 paths in the schedule network diagram to get from Project Start to Project Finish.

Path ACI which takes 22 days

Path BDE which takes 18 days

Path HJ which takes 5 days

Path FK which takes 14 days

Which of these four paths has a slack (float) time of 4 days? Select and save answer.

BDE

ACI

HJ

FK

None of these paths have a slack time of 4 days