Question: A project manager has mapped out that there are 4 paths in the schedule network diagram to get from Project Start to Project Finish. Path
A project manager has mapped out that there are 4 paths in the schedule network diagram to get from Project Start to Project Finish.
Path ACI which takes 22 days
Path BDE which takes 18 days
Path HJ which takes 5 days
Path FK which takes 14 days
Which of these four paths has a slack (float) time of 4 days? Select and save answer.
| BDE | ||
| ACI | ||
| HJ | ||
| FK | ||
| None of these paths have a slack time of 4 days |