Question: A project manager implemented an approved change to manage a risk. Three months after the implemented change, the project manager learns that there are new

A project manager implemented an approved change to manage a risk. Three months after the implemented change, the project manager learns that there are new risks because of implementation of the response. What is this called? SELECT THE CORRECT ANSWER Secondary risk Primary risk Residual risk Business risk