Question: A project manager is approached by an organization to develop the resource planning for their new innovative project. Even though the project manager has worked
A project manager is approached by an organization to develop the resource planning for their new innovative project. Even though the project manager has worked with many similar organizations in the past, this time, they are skeptical about the projects business model. Should the project manager use historical information in this case?
Yes, since historical information can provide insight when making comparisons to resources used on previous similar projects.
No since every project is unique, there is rarely any correlation between different projects resource expectations.
Yes, since an accurate estimation of resources cannot be performed without referring to historical information.
No since historical information is usually not applicable for innovative and rapidly changing projects.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock