Question: A project manager is assigned to a project at its onset. He needs to complete the initiating processes before he can continue with the remaining
A project manager is assigned to a project at its onset. He needs to complete the initiating processes before he can continue with the remaining project management processes. In addition to the project charter, what does he need in order to complete project initiating?
A project scope statement
A stakeholder register
A work breakdown structure
A scope management plan