Question: A project manager is building a project network that involves testing a prototype. She must design the prototype ( activity 1 ) , build the

A project manager is building a project network that involves testing a prototype. She must design the prototype (activity 1), build the prototype (activity 2), and test the prototype (activity 3). Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, she must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of: aGood network development. bHaving more than one start node. cConditional statements. dLooping.