Question: Bill is building a project network that involves testing a prototype. He must design the prototype ( activity 1 ) , build the prototype (

Bill is building a project network that involves testing a prototype.
He must design the prototype (activity 1), build the prototype (activity 2), and test the prototype (activity 3).
Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity
3. If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of
Looping
Natural network flow
Conditional statements
Having more than one start node
Good network development
 Bill is building a project network that involves testing a prototype.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!