Question: A project manager is determining the activity durations for completing an interior office building. The activities include installing 9 5 0 lineal feet of 3

A project manager is determining the activity durations for completing an interior office building. The activities include installing 950 lineal feet of 358''10' high metal stud walls, installing gypsum board on both sides, and finishing the gypsum board to a level 5 finish. Using the PERT formula, determine the expected duration of each activity.
Optimistic time to install metal stud walls =16 days
Most likely time to install metal stud walls =25 days
Pessimistic time to install metal stud walls =28 days
PERT Formula: TE=(O+4M+P)6
TE=
Optimistic time to install gypsum board =12 days
Most likely time to install gypsum board =16 days
Pessimistic time to install gypsum board =26 days
PERT Formula: TE=(O+4M+P)6
 A project manager is determining the activity durations for completing an

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!