Question: A project manager is evaluating a project's performance using Earned Value Management ( EVM ) . At month six, the Planned Value ( PV )
A project manager is evaluating a project's performance using Earned Value Management EVM At month six, the Planned Value PV is $ the Earned Value EV is $ and the Actual Cost AC is $ What does this indicate about the project's schedule and cost performance?The project is ahead of schedule and under budget.The project is behind schedule and over budget.The project is behind schedule but under budget.The project is on schedule but over budget.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
