Question: A project manager is faced with making a decision about a risk that the team has identified. The risk involves the design of a bicycle.
A project manager is faced with making a decision about a risk that the team has identified. The risk involves the design of a bicycle. It has been found that the neck of the bicycle, where the steering bearing is located and the two supporting bars of the frame come together, will corrode in a high salt environment. If this takes place the neck may fail and injure the rider. The project team decides that the design of the bicycle should be modified by using corrosion resistant materials in the design of the neck. This will eliminate the risk from consideration. This technique is called:
ARisk avoidance.
BRisk acceptance.
CRisk rejection.
DRisk deflection.