Question: A project manager is faced with making a large decision about a risk that her project team has identified. The risk involves the design of
A project manager is faced with making a large decision about a risk that her project team has identified. The risk involves the design of a car component.
It has been found that the weld of the component where the load-bearing flange is located will corrode in a high salt environment. If this takes place, the component may fail and injure the driver and passenger. The project team decides that the design of the component should be modified by using corrosion-resistant materials. This will eliminate the risk from consideration. What is this risk response technique called?
A: Risk rejection B: Risk acceptance C: Risk avoidance D: Risk transference
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
