Question: A Project Manager is handling a Project as per details mentioned below. He is interested in finding critical path for the project along with total
A Project Manager is handling a Project as per details mentioned below. He is interested in finding critical path for the project along with total float for each node. Help him by giving the solution to this problem. (7)
| Activity | Predecessor | Duration (Days) |
| A | -- | 5 |
| B | A | 4 |
| C | A | 3 |
| D | A | 2 |
| E | B | 8 |
| F | C | 7 |
| G | D | 6 |
| H | E,F,G | 4 |