Question: A project manager is leading a project to build a bridge. The initial plan called for the trusses to be painted. However, an external consultant
A project manager is leading a project to build a bridge. The initial plan called for the trusses to be painted. However, an external consultant has recommended to use powder coating for better protection against corrosion, and the recommendation has been accepted. As it pertains to the acquisition of resources, what should be done next?
Group of answer choices
Deny the recommendation as it represents gold plating
Follow the resource management plan
Purchase the powder coating equipment and supplies
Submit a change request