Question: A project manager is leading a project to build a bridge. The initial plan called for the trusses to be painted. However, an external consultant
A project manager is leading a project to build a bridge. The initial plan called for the trusses to be painted. However, an external consultant is now recommending the use of powder coating for better protection against corrosion, and the team thinks this a good recommendation. What should be done next? Group of answer choices Follow the resource management plan Purchase the powder coating equipment and supplies Submit a change request Deny the recommendation, as it represents gold plating