Question: A project manager is managing a project for a govemment owned company using an iterative approach: The first useful release to. production consisted of three
A project manager is managing a project for a govemment owned company using an iterative approach: The first useful release to. production consisted of three iterations. Fach iteration was successfully checked by the client's representatives in the test environment However when the team started deploving to the production environment, the security team declined it What should the project manager have done to prevent this? Implemented the authorization in the first iteration Deployed to production after the first iteration Reviewed the compliance requirements with stakeholders Planned smaller iterations to review the results more often
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock