Question: A project manager is managing a project. The original scope baseline of the project was budgeted at $200,000. Since work on the project started there
A project manager is managing a project. The original scope baseline of the project was budgeted at $200,000. Since work on the project started there have been twelve authorized and approved changes to the project. The changes have a value of $15,000 and the cost of investigating them prior to their approval was $2,000. What is the current budget for the project?
|
|
$200,000
|
|
|
$213,00
|
|
|
$215,000
|
|
|
$217,000
|