Question: A project manager is managing a wed - based application project to automate the accounting processes of his organization. The project has an estimated budget
A project manager is managing a wedbased application project to automate the accounting processes of his organization. The project has an estimated budget of and a duration of nine morths, While reviewing the project, the project munager notec that activines were scheduled in sequential order, but coding work was iirated elve days earlier than planned. What moe of
relstionship represent the start of the reding wark to the completion of the design werk?
Finishcostart reiationship with a awelve day lag.
Finistscart relationship with a velve day lead
Startofinisi with a twelveday lag
Starttofinish with a twelve day lead