Question: A project manager is managing a wed - based application project to automate the accounting processes of his organization. The project has an estimated budget

A project manager is managing a wed-based application project to automate the accounting processes of his organization. The project has an estimated budget of 120000 and a duration of nine morths, While reviewing the project, the project munager notec that activines were scheduled in sequential order, but coding work was iirated elve days earlier than planned. What moe of
relstionship represent the start of the reding wark to the completion of the design werk?
Finish-co-start reiationship with a awelve day lag.
Finis/-t0-scart relationship with a (velve day lead
Star-to-finisi with a twelve-day lag
Start-to-finish with a twelve day lead

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!