Question: A project manager is managing an agile project where the team is regularly missing user story due dates. What should the project manager do to

A project manager is managing an agile project where the team is regularly missing user story due dates. What should the project manager do to resolve this situation?
A.Work with the sponsor to move out the deliverable hand over date.
B.Review the time allotted to iterations and sprints, adjusting them as needed.
C.Meet with the project team to identify if further agile methodologies training is necessary.
D.Implement a reward program for the project team to encourage completing stories on the due dates.