Question: A project manager is mantaging a project that has reached the end of the planning phase. The work scope has been agreed to and definitive
A project manager is mantaging a project that has reached the end of the planning phase. The work scope has been agreed to and definitive cost esfiriates have been completed for the project. The lotal estimated cost of the project is $300,000. it is reasonable to expect that the project will not cost over which of the following value? Select one: sin0,000 $330,000 $220,000 5310,000